    Hello dear Espo community,

    I have a question about BPNM.

    The process creates a task for me (not a user task).

    After the task has been created, the process should only continue when this task has been set to "Done". Does anyone have an idea how I can do this? Unfortunately, signal events or exclusive gateways don't work.

    Thanks and best regards, Chris​

  • #2
    Hi ChriscCross,

    In this case, you can use a Conditional Intermediate Event (Catching): https://docs.espocrm.com/administrat...event-catching.

    Comment


    • #3
      attached a screenshot of what you need to do using the Conditional Intermediate Event (Catching).