Continue the process after a task has been reported as completed.

Collapse
X
 
  • Time
  • Show
Clear All
new posts
  • ChrisCross
    Junior Member
    • Jun 2022
    • 14

    Continue the process after a task has been reported as completed.

    Hello dear Espo community,

    I have a question about BPNM.

    The process creates a task for me (not a user task).

    After the task has been created, the process should only continue when this task has been set to "Done". Does anyone have an idea how I can do this? Unfortunately, signal events or exclusive gateways don't work.

    Thanks and best regards, Chris​
  • lazovic
    Super Moderator
    • Jan 2022
    • 809

    #2
    Hi ChriscCross,

    In this case, you can use a Conditional Intermediate Event (Catching): https://docs.espocrm.com/administrat...event-catching.

    Comment

    • rabii
      Active Community Member
      • Jun 2016
      • 1250

      #3
      attached a screenshot of what you need to do using the Conditional Intermediate Event (Catching).

      Click image for larger version

Name:	Screenshot 2024-12-01 at 12.29.29.png
Views:	34
Size:	296.1 KB
ID:	112697
      Rabii
      Web Dev

      Comment

      Working...