    I have setup a report to output overdue tasks. However, on IsOverdue to any filter (Static or Runtime) results in the report getting stuck. Even adding the field to the parameter list results in the report getting stuck.

    Can you please advise?

  • #2
    Hi

    Create Report with filter 'Date Due': Past. That's the same as Overdue. isOverdue is UI only field. We will need to remove it somehow from the list of filters.

    Comment


    • #3
      Didn't realize it was a UI only field. The behavior makes sense now. Will create a report with date due. Thanks.